How It Works

The work starts long before installation.

A good fence begins with a complete picture. We learn what you want, walk the property, measure the layout and look for the details that could affect the job. Then we build a clear plan and carry it through.

Before the First Post

Look first. Plan well.
Build once.

The estimate visit is not just about measuring footage. It is where we study the property, confirm the layout and identify the details that matter before installation begins.

AccessGradeLandscapingExisting fencingConcreteGate clearancesUtilitiesProperty linesPool requirementsHOA rulesCity requirements

The goal is simple: understand the complete project before we price it, permit it or build it.

The Process at a Glance

Nine stages.
One controlling plan.

Every project moves through the same structure, whether it needs a permit or not. Some stages move quickly. Others depend on a city, an association or the weather.

01

Project Details

We begin with the property, the fence you are considering and what you need it to accomplish.

02

Site Visit

We measure, photograph and inspect the proposed fence line for anything that could affect design, pricing or installation.

03

Estimate + Approval

You receive a written proposal based on the information gathered. Approval and the initial payment launch the project.

04

Documents + Permitting

When required, we prepare the contractor, engineering and permit documents needed for city review, plus supporting documents for your HOA submission.

05

Project Preparation

After approval, we verify the project, calculate materials and prepare any standard, special-order or custom-fabricated components.

06

Scheduling + Utility Locate

We coordinate the installation window and request a Sunshine 811 utility locate before digging.

07

Installation

Our crew installs the approved project. Most standard residential installations take approximately one to three working days.

08

Inspection + Closeout

After installation and final payment, we schedule required city inspections and close the permit after approval.

09

Workmanship Warranty

Qualifying installations are supported by Power Fence's three-year limited workmanship warranty.

Open every stage ↓

The Details

Open a stage.
See the whole picture.

Every property is different. Open each stage to see what happens, what we handle and what we may need from you.

01Project Details

First, we understand what you are building.

We begin by gathering the basic project information: property address, preferred fence material, height, style, color, gate needs and proposed location.

We also ask about the reason for the fence. Privacy, pool safety, pets, security, waterfront conditions and HOA requirements can all affect the right design.

What Power Fence Handles
  • Initial project discussion
  • Material and style guidance
  • Preliminary project qualification
  • Scheduling the appropriate onsite or virtual estimate
  • Requesting an available property survey
What We Need From You
  • Accurate property and contact information
  • A general idea of the desired fence layout
  • Material and style preferences
  • HOA information, when applicable
  • A property survey, when available
  • Information about pools, pets, gates or special access requirements
02Site Visit

We look for more than footage.

The purpose of the estimate visit is to build a complete picture of the project. We measure the proposed fence line, discuss gate placement and inspect the conditions that may affect the installation. Catching these details early helps us price the correct work and prevent surprises later.

  • Proposed fence location
  • Individual fence runs and footage
  • Gate size, location and swing direction
  • Pool-barrier requirements
  • Grade and elevation changes
  • Vegetation and required clearing
  • Existing fence removal
  • Neighboring fences and property-line conditions
  • Access for crews and materials
  • Concrete, pavers and mounting conditions
  • Drainage, irrigation and visible utilities
  • Areas that may require hand digging
  • Retaining walls, seawalls and unusual site conditions
  • Custom fabrication requirements
  • HOA or architectural restrictions

The site visit is also when we determine how the fence will be installed. Posts may be embedded in the ground, core drilled through concrete or mounted with engineered base plates. Those are different installations with different material and labor requirements.

Know where you want the fence and gates before the visit. If you have a survey, HOA guidelines or inspiration photos, have them ready. Better information produces a better estimate.

03Estimate + Approval

The plan becomes a proposal.

After the visit, we prepare a written estimate based on the approved layout, materials, gates, removal and known property conditions. The proposal describes what Power Fence is providing and identifies the drawing or layout associated with the work.

Once the proposal is signed and the 30% initial payment is received, the project officially launches.

What Power Fence Handles
  • Preparing the written scope and pricing
  • Documenting the proposed fence and gate layout
  • Confirming whether permitting or HOA approval applies
  • Identifying known allowances, options and exclusions
  • Creating the customer's project record
What We Need From You
  • Signed proposal
  • 30% initial payment
  • Property survey
  • Confirmation of HOA requirements
  • Timely approval of the proposed layout and selections

The approved proposal and drawing become the foundation of the project. Changes to footage, materials, gates, mounting conditions or layout may affect price, permitting, materials and scheduling.

04HOA Documents

We provide the support. You submit to your association.

If your property has an HOA, we provide the contractor documents and project information commonly requested by associations. The homeowner is responsible for completing the HOA's application, submitting the package and obtaining written approval.

Power Fence May Provide
  • Certificate of insurance
  • Contractor license
  • Marked property survey
  • Fence product or style photograph
  • Signed proposal
  • Proposed fence layout
  • Other available contractor documentation reasonably required for the submission
What We May Need From You
  • HOA application and instructions
  • Certificate-holder information
  • HOA contact information
  • Required design standards
  • Written approval once issued
  • Any comments or requested revisions from the association

HOA approval and city permit approval are separate. Receiving one does not automatically provide the other.

05Permit Preparation

Before the city reviews it, we build the permit package.

Permit-required projects involve more than a one-page application. The complete package may include a marked survey, notarized forms, recorded documents, utility-easement approvals and signed and sealed engineering. We review the project documents before submission to confirm that the proposal, drawing and permit layout agree.

Power Fence May Handle
  • Reviewing the survey for readability and permit use
  • Marking the proposed fence location, measurements and fence type
  • Preparing and notarizing applicable permit forms
  • Ordering signed and sealed engineering when required
  • Preparing applicable affidavits
  • Recording required documents with the county
  • Obtaining applicable utility or easement approvals
  • Submitting the complete package through the city portal or in person
  • Tracking the permit number and review status
  • Responding to ordinary city comments
What We May Need From You
  • A complete and readable property survey
  • A valid copy of the property owner's identification when required
  • Signed permit documents
  • Accurate ownership information
  • HOA approval when required before permit issuance
  • Prompt signatures or responses if the city requests additional information

Engineering requirements depend on the city, fence material, design, height and gate size. PVC, aluminum, horizontal fencing and larger gates may require signed and sealed drawings.

A survey identifies legal property information. Field measurements determine the actual amount of fencing required. If the approved layout or footage changes, the proposal and permit documents may also need to change.

06City Review

The city takes it from here. We stay with it.

Once submitted, the permit may be reviewed by several departments, including zoning, structural, landscaping and engineering. A standard review commonly takes approximately four to six weeks, but timing varies by municipality, workload, corrections and project complexity. Power Fence follows the permit and responds when comments are issued.

What Power Fence Handles
  • Monitoring the permit status
  • Responding to routine corrections
  • Coordinating revised documents when needed
  • Reviewing technical questions with the estimator, foreman, engineer or project team
  • Informing the customer of material changes
  • Resubmitting corrected documents
What May Affect Timing
City workloadIncomplete or outdated surveysEasement approvalEngineering revisionsLandscaping or setback requirementsHOA requirementsOwnership discrepanciesChanges to the requested fenceAdditional city comments

We manage the process. We do not control the city's review calendar.

When the Plan Changes

If the city, customer or site conditions require a change to the approved scope, Power Fence will explain the change before proceeding whenever reasonably possible.

Additional footage, revised layouts, different materials, added gates, changed mounting methods and permit revisions may require a written change order. Permit revisions can carry additional city, engineering, recording and administrative costs. The goal of the original site visit is to identify these items early — not discover them during installation.

  • Actual fence footage differs from the permitted layout
  • A fence must be moved because of property-line or easement conditions
  • Closing a gap creates additional footage
  • A neighbor's fence cannot legally be removed without authorization
  • Concrete requires core drilling or base-plate mounting
  • The city requires additional landscaping setbacks
  • A gate or design requires additional engineering
07Permit Approval + Project Preparation

Approved. Now we prepare the build.

Once the permit is approved, we organize the approved documents, verify the project and prepare the information needed by purchasing, fabrication and the installation crew. The approved permit drawing becomes the controlling layout for the permitted work.

Power Fence Handles
  • Confirming the permit approval date
  • Reviewing the approved survey and plans
  • Removing outdated drawings from the active job packet
  • Calculating final material quantities
  • Estimating the number of installation days
  • Preparing office and field job packets
  • Ordering standard materials
  • Coordinating supplier deliveries
  • Preparing chain-link or specialty material orders
  • Finalizing gate, latch and hardware requirements
  • Identifying custom fabrication work

One approved plan. One current job packet. One version for the team to follow.

08Materials + Scheduling

Materials first. Date second.

Scheduling typically begins after permit approval and final project review. Standard projects are commonly scheduled approximately three to four weeks after permit approval, depending on material availability, current workload, project size and weather.

Before the installation date is finalized, Power Fence confirms the project requirements and requests the scheduled 50% progress payment, applicable permit fees and signed pre-installation terms.

What Power Fence Handles
  • Material orders
  • Supplier coordination
  • Delivery planning
  • Crew-duration planning
  • Proposed installation dates
  • Customer scheduling communication
  • Pre-installation paperwork
What We Need From You
  • Confirmation that the proposed dates work
  • 50% progress payment
  • Payment of applicable permit and engineering fees
  • Signed pre-installation terms
  • Completion of required vegetation, grading or access preparation
  • Confirmation that the approved layout has not changed

All timeframes are typical estimates — not guaranteed completion dates. Permits, HOA decisions, weather, material availability, customer changes and fabrication requirements can affect the schedule.

09Sunshine 811 + Site Readiness

Before we dig, utilities get marked.

Power Fence submits a Sunshine 811 locate request before the scheduled installation so participating utility operators can mark applicable underground facilities.

Sunshine 811 does not necessarily identify private utilities or customer-owned systems. Irrigation, pool lines, landscape lighting, low-voltage wiring, private electrical lines, drainage and other private installations may require separate identification by the property owner or a private locating service.

Power Fence Handles
  • Submitting the applicable Sunshine 811 request
  • Monitoring the locate window
  • Providing the customer with a pre-installation update
  • Reviewing obvious conflicts when markings appear
What We Need From You
  • Clear access to the installation area
  • Required landscaping and vegetation work completed
  • Pets secured
  • Vehicles and stored items moved
  • Private utilities identified
  • Changes to the property disclosed
  • The approved layout kept available and unobstructed
10Installation

Then we build.

Our crew installs the fence according to the approved scope, layout and available permit documents. Most standard residential projects take approximately one to three working days. Larger projects, difficult access, custom fabrication, concrete work and unexpected site conditions may require additional time.

Power Fence Handles
  • Delivering the planned materials
  • Installing the approved fence and gates
  • Following the current job packet
  • Managing normal installation cleanup
  • Communicating material site conditions or required changes
  • Preparing the project for closeout

Please do not request unapproved field changes directly from the crew. Layout, material or scope changes must be documented through the office and may require a change order or permit revision.

11Final Payment + Inspection

Installed is not always closed.

After installation, Power Fence sends the final payment request. Once the account is paid according to the agreement, we request the required final city inspection.

In most cases, the homeowner does not need to be present for the inspection. Power Fence monitors the result and addresses ordinary workmanship-related inspection corrections within the contracted scope.

Power Fence Handles
  • Final payment documentation
  • Paid-in-full invoice
  • Scheduling the city inspection
  • Sending available inspection-date information
  • Monitoring inspection results
  • Closing the permit after approval
  • Communicating required corrections or revisions

If the installed layout differs from the city-approved plan because of a customer-requested change, undisclosed condition or changed field measurement, the city may require a permit revision. Additional city, engineering, documentation and labor charges may apply.

12Workmanship Warranty

Our name stays on the work.

Qualifying Power Fence installations include a three-year limited workmanship warranty. If a covered problem results from how we installed the fence, we will inspect it and correct the affected workmanship according to the warranty terms.

Read the Full Workmanship Warranty

Made Here Takes a Little Longer

Custom-welded aluminum is measured, drawn, fabricated and finished specifically for the property, following its own path: a final field measurement to confirm exact dimensions, a shop drawing the customer reviews and confirms before fabrication, hardware selection for latches and keypad locks, then cutting, assembly, welding and powder-coat finishing before scheduling. Fabrication commonly takes approximately three to five weeks, followed by approximately two to three weeks for powder coating, depending on project size and production conditions. Upgrades to hardware may require a written change order, and projects of $20,000 or more may carry additional progress-payment milestones as described in the signed agreement.

Measured for your property. Built by hand. Finished to order.

For Planning Purposes

A typical
permitted project.

Project launch
Begins after signed approval and 30% initial payment
HOA and permit preparation
1–3 weeks after receiving complete documents
City review
4–6 weeks after submission
Standard project scheduling
3–4 weeks after permit approval
Custom fabrication
Additional fabrication and finishing time
Standard residential installation
1–3 working days
Final inspection
Scheduled after installation and final payment

These are typical ranges, not guaranteed dates. City review, HOA approval, engineering, easements, material availability, weather, customer changes and project complexity may affect the timeline.

Field measurement being taken before fabrication

Two Routes

Does your project
require a permit?

Project approval→Documents→Permit preparation→City review→Permit approval→Materials and scheduling→Utility locate→Installation→Inspection and closeout
Project approval→Final project review→Materials and scheduling→Utility locate→Installation→Payment and closeout

Permit requirements are determined by the applicable jurisdiction and project conditions. A project only follows the non-permit path when Power Fence confirms that path in writing.

Questions

Frequently asked.

What should I have ready for the estimate visit?

Know where you want the fence and gates before the visit. If you have a survey, HOA guidelines or inspiration photos, have them ready. Better information produces a better estimate.

Why does Power Fence request a property survey?

A survey identifies legal property information. Field measurements determine the actual amount of fencing required. Together they help us price, permit and design the project correctly.

Does Power Fence handle my HOA application?

We provide the contractor documents and project information commonly requested by associations. The homeowner is responsible for completing the HOA's application, submitting the package and obtaining written approval, unless otherwise agreed in writing.

Is HOA approval the same as a city permit?

No. HOA approval and city permit approval are separate. Receiving one does not automatically provide the other.

How long does permitting usually take?

A standard review commonly takes approximately four to six weeks after submission, but timing varies by municipality, workload, corrections and project complexity.

Why might the city request corrections?

Corrections can come from an outdated survey, an easement that needs approval, an engineering revision, a landscaping or setback requirement, or an HOA condition. We respond to routine corrections as part of permit preparation.

What happens after my permit is approved?

We organize the approved documents, verify the project, calculate final material quantities and prepare the job packets that purchasing, fabrication and the installation crew work from. The approved permit drawing becomes the controlling layout.

When is the second payment due?

The 50% progress payment is requested before the installation date is finalized, along with applicable permit fees and signed pre-installation terms.

What does Sunshine 811 mark?

Sunshine 811 notifies participating utility operators to mark applicable underground facilities before digging.

Do I need to identify irrigation and private utilities?

Yes. Irrigation, pool lines, landscape lighting, low-voltage wiring, private electrical lines, drainage and other private installations may require separate identification by the property owner or a private locating service.

How long does installation normally take?

Most standard residential projects take approximately one to three working days. Larger projects, difficult access, custom fabrication, concrete work and unexpected site conditions may require additional time.

Why do custom-welded projects take longer?

Custom-welded aluminum is measured, drawn, fabricated and finished specifically for the property. Fabrication commonly takes approximately three to five weeks, followed by approximately two to three weeks for powder coating, depending on project size and production conditions.

What happens if I change the layout?

Changes to footage, materials, gates, mounting conditions or permit layout may require a written change order and can affect price, permitting, materials and scheduling.

When is the final inspection scheduled?

After installation and once the final payment is received, Power Fence requests the required city inspection. In most cases, the homeowner does not need to be present.

What happens if an inspection requires a correction?

Power Fence monitors the result and addresses ordinary workmanship-related corrections within the contracted scope. If the installed layout differs from the approved plan because of a customer change or undisclosed condition, a permit revision and additional charges may apply.

What warranty comes with the installation?

Qualifying installations include a three-year limited workmanship warranty covering problems that result from how the fence was installed.

Have a question we didn't cover?

Start With the Property

Tell us what you're planning.

A few project details are enough to begin. We'll help you understand the options, schedule the right type of estimate and build the plan from there.

Broward & Palm Beach Licensed & Insured

Financing available

Fence now. Pay over time.

Power Fence can help customers explore monthly payment options through Wisetack for eligible fence, gate, and railing projects.

UP TO 25K ELIGIBLE PROJECTS Fast customer prequal No prepayment penalty

Ask about financing

Financing subject to credit approval. Payment options are provided by Wisetack lending partners.